Aerial view of the tank farm with large crude tanks, smaller product tanks and the flare tower

Site and logistics

A coastal site with deep water and the port next door

The process core sits on a 125 ha parcel on the Raysut plateau in the Salalah Free Zone. Storage, the flare and the marine links occupy adjacent land; crude arrives by single-point mooring and products leave through the Port of Salalah.

Concept visualisation

Location

Salalah Free Zone, Raysut, Dhofar

The parcel lies on the Raysut limestone plateau, 20–53 m above sea level, inside an operating industrial cluster on the western side of Salalah.

The Port of Salalah liquid berths are 4.3–4.6 km to the east-north-east, the free-zone 132 kV grid station is about 0.6 km away and the cliff coast is 1.7 km to the south. Deep water lies close inshore.

The design allows for Mekunu-class rainfall, cyclone surge and the Khareef monsoon swell of June to September, which limits marine works to December–April.

Site plan

The phase-1 layout

Plot plan Rev 1 places the process core, utilities and buildings on the parcel, and the tank farm, flare and marine links on adjacent land.

Top-down view of the refinery site layout on satellite imagery
Concept visualisationSite plan, north up: the process core on the parcel (top right), the storage lease south of the road, the flare site (bottom) and the landfall and desalination plots on the coast (right).

Land

Phase-1 land requirement

Phase-1 land requirement in hectares
AreaHectaresUse
Process parcel125Process units, utilities, buildings and four hot intermediate tanks
Storage lease≈95Crude, product and LPG tanks, truck loading, tank-farm firewater and fire post
Flare site≈15150 m elevated flare about 1.6 km south-west of the process core
Corridors≈10Pipelines, landfall valve station, desalination, and coke and sulphur stores
Construction laydown≈52Temporary, during construction only
Permanent land take≈245Plus about 52 ha of temporary laydown

The parcel hosts the process core. Storage, the flare site, the corridors and expansion land are adjacent requirements to be secured with the free-zone authority.

A second train would need about 130 ha more. Plot plan Rev 1 draws about 96 ha of it on land south of the road, subject to a written reservation before the phase-1 investment decision.

A very large crude carrier moored to a buoy at sea, with the coast behind
Concept visualisationCrude import

Crude import

Single-point mooring for Suezmax and VLCC tankers

A single CALM buoy in 38–39 m of water, about 2.55 km off the coast south-south-east of the parcel, receives crude from Suezmax and VLCC tankers.

Two 42-inch lines, sized for 300,000 bpsd from the start, run 2.71 km subsea, cross the shore by a 0.59 km horizontal directional drill and continue about 2.1 km onshore to the crude tanks, through a landfall valve station set back from the cliff.

A 500 m safety zone, a one-nautical-mile area to be avoided and a no-anchoring corridor protect the buoy and its lines. Twenty-five days of owned crude in the tank farm bridge the Khareef season, when swell reduces mooring availability.

From mooring to market

How crude and products move

Crude in

  1. Single-point mooring38–39 m of water, about 2.55 km offshore
  2. Subsea lines2 × 42-inch, 2.71 km to the shore crossing
  3. Shore crossing0.59 km horizontal directional drill
  4. Landfall valve stationThen about 2.1 km of onshore lines
  5. Crude tanksSix tanks on the storage lease, 4.4 mn bbl

Products out

  1. RefineryProcess core on the 125 ha parcel
  2. Product and LPG tanksOn the storage lease, about 16 days of finished products
  3. Export pipelinesAbout 7.5 km along the free-zone pipe-rack corridor
  4. Port of SalalahLiquid berths 1–2 and a third berth to be secured
  5. Product tankersAbout 150 cargoes a year to market

About 5.8 million tonnes a year of liquid products: about 5.6 Mt over the port’s liquid berths and about 0.2 Mt of LPG through an existing LPG jetty, subject to its owner’s consent.

Product export

Through the Port of Salalah

Phase 1 has no dedicated product jetty. All liquid products leave through the Port of Salalah under a throughput agreement.

  • 01

    Liquid berths 1–2

    Two 300 m berths with an 18 m draft, which handled 3.43 Mt of liquid bulk in 2025 against a nominal 6 Mt a year.

  • 02

    A third liquid berth

    Headroom on berths 1–2 at start-up is only about 1.3 Mt a year, so a third liquid berth, which the throughput agreement must secure and which must be in service by early 2034, is a condition of the investment decision.

  • 03

    Fallback

    If the third berth or the throughput agreement cannot be secured, the fallback is a sheltered product jetty with a breakwater.

Storage

8.4 million barrels of operating tankage

28 tanks for crude, finished products, intermediates and 0.5 mn bbl of bunker and merchant storage, plus separate refrigerated and mounded LPG storage.

  • 01

    Crude

    4.4 mn bbl in six floating-roof tanks, each in its own bund cell: about 25 days of usable crude.

  • 02

    Finished products

    2.7 mn bbl for diesel, jet fuel, gasoline and naphtha: about 16 days of finished products.

  • 03

    Intermediates

    0.8 mn bbl, including hot VGO and residue tanks on the parcel that buffer unit outages.

  • 04

    LPG

    Two 12,300 m³ refrigerated full-containment tanks and two 2,570 m³ mounded bullets, which replace spheres and remove the risk of a fire escalating to the crude tanks.

Enquiries

Talk to the development team

For investor, lender, partner and media enquiries, write to us. Public documents are on the Downloads page.